Report on the Charles River Crossing

Bridge Design Review Committee, October 1991

This 150 report contains a great deal of visual material, which will not reproduce well on the web. The parts excerpted here are from its Executive Summary.


Summary of Initial Committee Concerns

Committee members were asked to submit their concerns with Scheme Z in writing. Letters received are included in the Appendix. Improvements and concerns suggested in these letters are summarized below:

· Restore the Traverse Street on-ramp or an equivalent move to reduce additional traffic on local streets and negative noise and air quality impacts.

· Reduce visual impacts of bridge and ramp height/massing to improve visual design.

· Ensure positive development/design of parklands along the Charles River Basin, which is adversely affected by Scheme 7.

· Investigate alternative schemes, including partial and/or full tunnel alternatives, to find a superior solution to the river crossing.

· Reduce negative impacts of bridge piers and overhead structures on aquatic resources and navigation in the Charles and Millers Rivers and on open space along their banks.

· Incorporate/improve nonautomobile transportation, including pedestrian and bicycle routes, ferry service at Lovejoy Wharf, and bus and high-occupancy vehicle (HOV) routes.

· Provide pedestrian and bicycle routes along both banks of the Charles River and connections both to and across the river from Charlestown, Cambridge, and Boston.

· The Committee's work should not unduly delay the Artery/Tunnel or CANA projects or jeopardize funding.

· Provide adequate technical support to Committee deliberations.

· Maintain/review all connections to the regional roadway system. Give special consideration to the role played by Storrow Drive in the regional system and maintain its character as part of the Esplanade.

· Minimize construction impacts; maintain road and transit connections during construction.

Narrowing the Options

The Committee began with the broadest possible spectrum of ideas, from members and nonmembers alike, for improving the Charles River crossing. The problem was disaggregated into component parts, and several options were considered for each of these components. Beginning early in April 1991, packages were assembled from these component parts and denoted Committee Improvement Packages (CIPs) 1 to 13.

Committee Improvement Packages were of several types. CIPs 1 and 2 are variations of Scheme Z. CIP 3 would provide access between Storrow Drive and the north on a bridge over the Charles River. CIP 4 would use arterial street connections with a low bridge over the Charles River. CIPs 5 and l1 would make the connections between Storrow Drive and the North via tunnels under the Charles River. CIP 6 would have multiple tunnels under the Charles for Storrow Drive and Traverse street connections. CIP 7/10 would place both mainlines and Storrow Drive connections in river tunnels. CIPs 8 and 12 are hybrids that would have eastbound Storrow Drive connections to the north in tunnel and westbound connections from the north on a bridge. CIPs 9 and 13 are similar to CIPs 8 and 12 but also carry northbound Artery traffic to the Tobin Bridge in the river tunnel.

Packages were improved by incorporating bridge and tunnel concepts suggested by the Committee's expert contributors as well as design refinements developed by the CA/T engineering staff. Most packages were studied in several versions differing in the design of ramp connection north of the river, Leverett Circle access, single- versus double-deck bridge, and exclusive HOV ramps. Ramp variations explored for CIPs 3, 5, and 8 included different combinations of loop ramps over and under the MBTA commuter railroad tracks near the north bank of the Charles River, left-hand and right-hand Artery exits to the Tobin Bridge, and combination of Tobin Bridge and Storrow Drive loop Connections. Options for connecting Storrow Drive to northbound 1-93 were also explored for CIPs 5 and 8. These variations increased the total number of options that received engineering study to over 20.

After the first round of study, all packages had basically the same geometry south of Causeway Street: connections between the central area of the Artery and Leverett Circle via a pair of tunnels behind North Station. This geometry solves the inadequate traffic weaves of the alternatives studied with Scheme Z in the SEIS, it eliminates Scheme Z's double river crossings, and it permits reintroduction of a northbound on-ramp without additional structures in the Charles River. It is emphasized that the south of Causeway Street geometry is a prerequisite for the improvements studied by the Committee for improving Charles River bridge design and for reducing impacts to Charles River open space by lowering the loop ramps; those improvements are not geometrically possible if the additional ramps required for Scheme Z's double river crossing must be accommodated.

Packages were evaluated by the Committee and its three subcommittees, using objectives developed by each of them. Special concern was focussed on resources protected by Section 4(f). Packages differed both in potential impacts due to their Charles River bridges and ramps and in the changes they would make to Storrow Drive next to the Charles River Esplanade, one of the premier parklands in the region. Packages also differed in terms of visual and land use impacts, traffic, and access. Issues of concern to the Committee in evaluating these options included the adequacy of access to Leverett Circle and the North Station area; future traffic volumes on Storrow Drive and the Charles Street Extension, and implications for the roadway's cross-section and for the accessibility and quality of the adjacent Charles River Esplanade; impacts to the North Point area of Cambridge, the Charlestown residential community, and North Station area development; the symmetry and aesthetics of the Charles River bridge and related opportunities for HOV access and pedestrian/ bicycle use; and the coverage of the Charles and Millers River by the bridge and associated viaducts. All packages were subjected to detailed scrutiny and discussion.

Among the packages studied but eliminated from consideration in the final round were two versions of the all-tunnel option. Known as CIP 7/10, this concept was favored by a number of members because of its open space and visual benefits, but it was ultimately not advanced because of cost and other issues. Other packages not advanced were CIPs 1 and 2, which were judged not sufficiently improved from Scheme Z. CIP 4 (arterial bridge) had bridge and traffic impacts. CIP 6 involved multiple river tunnels and open space impacts. CIPs 11 and 12 (tunnel parallel to bridge) were similar to CIPs 5 and 8 but more costly and with additional land use impacts. CIPs 9 and 13 reduced mainline bridge width by carrying one 1-93 lane in a tunnel but posed traffic operation difficulties.

On May 23,1991, at a joint meeting of the subcommittees, Packages 3, 5, and 8 were advanced for further consideration. This final round of scrutiny led to several improvements, variations and modifications, which are described in the body of this report.

In the final week of Committee deliberations, these variations were reduced to final versions of Packages 3, 5, and 8. In a 17-15 vote on June 2l, 1991, the Committee recommended CIP 8 over CIP 5.

On the following pages are Committee Chairman Stanley Miller's statement to the Committee, the summary information used by the Committee in comparing the packages, and the recommendations adopted by the Committee.

While these final packages shared several key improvements such as eliminating double river crossings and providing northbound access to Route 1-93, and to varying degrees reduced ramp impacts along the north bank of the river, several key differences were the subject of the final deliberations. CIPs 5 and 8 have deeper and therefore longer boat sections than CIP 3 in Storrow Drive next to the Esplanade. While the current level of design shows no encroachment into the Esplanade by any package, there was concern that these boat sections would be visual and psychological barriers and might require temporary use of some land during construction, as well as some potential permanent 4(f) use of Esplanade land if the cross-section increases in width during the design process; (continued scrutiny is needed during the design process to avoid and minimize such impacts). Similarly, the width and height of the bridges and connecting ramps differ among the final packages with varying impacts on the Charles River and on existing, planned, and potential open space on both banks; CIP 5 has a narrower bridge than CIP 8 while CIP 3's ramp connections have more impacts than the other two packages. CIP 3 extends further into the North Point development area than the other packages. Northbound egress to Nashua Street is an important concern, and at present only CIP 5 provides this ramp. CIP 5 is highest, CIP 8 intermediate, and CIP 3 lowest in both cost and materials disposal requirements. These issues are compared in the Table on page 18.

Committee Recommendation

The Committee adopted the following recommendation on June 21, 1991:

To improve the Charles River crossing portion of the Central Artery/Tunnel Project in accordance with the mandate of the Secretary of Transportation in convening the Bridge Design Review Committee on February 1, 1991, the committee makes the following recommendations to the Secretary:

1. Abandonment of Scheme Z.

Each option still before this Committee (CIPs 3, 5, and 8) is a significant improvement over Scheme Z, in terms of traffic, open space and land use, and the visual appearance of the bridge and its associated ramps.

All options eliminate all double river crossings, thereby reducing vehicle miles travelled and reducing the number of lanes crossing the river from 16 in Scheme Z (or 18 if Ramp WCN had not been deleted), to a maximum of 13. Instead of Scheme Z's three bridges (or four if the WCN ramp had been included in the project), all the Committee options have only a single bridge, supplemented in two options by a tunnel or tunnels under the Charles River. All options reduce the height and the width of the bridge by about one-third. Scheme Z's six loop ramps in North Point have been reduced to either two or three, depending on the particular option. The bridge is far more visually appealing than Scheme Z's bridge.

In all Committee options, an on-ramp from downtown Boston to the north has been added to the plans, replacing the function of the former Traverse Street on-ramp that was deleted from Scheme Z.

Scheme Z is unacceptable to this Committee. We unanimously recommend that it be abandoned as a viable approach to crossing the Charles River.

2. South of Causeway Street/North Station Area.

The Committee unanimously recommends that the design of the CA/T Project south of Causeway Street and in the North Station area be modified to include the Sudbury on-ramp and direct connections between Leverett Circle and the downtown portion of the Central Artery and related design changes as included in all Committee Improvement Packages and as described in the Committee's Summary Report of May 15, 1991.

3. Recommended Committee Improvement Package: CPI 8.

We recommend that Committee Improvement Package 8, as presented to and endorsed by this Committee on June 21, 1991, be adopted as a substitute for Scheme Z, observing all applicable notification, environmental, and permitting requirements needed to make this plan part of the approved CA/T Project.

We recommend that the Secretary vigorously pursue design refinement; Federal and State funding sources that could reasonably be provided during the full construction period; and environmental and permitting approvals to incorporate this plan into the CA/T Project.

The construction of either CIP 8 or CIP 5 will add cost to the entire CA/T project. In seeking additional funds for the crossing, the State shall not apply funds for mitigation or improvements to the project in other Boston neighborhoods and areas along the project corridor as a source of funds to offset this increased cost.

The Committee recommends that nothing be done to expand either the capacity or geometry of Storrow Drive.

In the event that the Secretary determines, after a sustained good faith effort, that he is unable to support the Committee's first choice as his own, we request that he not move to another solution (including either of the Committee's other final options) without consultation with the Committee.

Description of CIP 8

· A single-deck bridge with two southbound lanes connecting from 1-93 and Tobin Bridge to Storrow Drive, four southbound 1-93 main line lanes, and five northbound 1-93 mainline lanes.

· A two-lane tunnel under the Charles River (one lane from Storrow Drive and one lane from Merrimac Street) to the City Square Tobin Bridge approach and 1-93 northbound.

· Northbound on-ramps at New Sudbury Street and Lomasney Way.

· Outer CANA ramp from Central Artery to Tobin Bridge (C-T) passes under the commuter rail tracks.

· Inner loop ramps from Tobin Bridge to Central Artery (T-C) and Tobin Bridge to Storrow Drive (T-S) are combined on a single three-lane viaduct

· The Storrow-to-north ramp (S-N) remains in tunnel to the Gilmore Bridge to avoid visual and noise impacts on Charlestown.

4. A Multidisciplinary Design Phase.

It is understood that this new Charles River crossing portion of the CA/T Project will require detailed preliminary and final design work. We recommend that the design phase be accomplished in a multidisciplinary manner, with involvement of professionals from engineering, architecture, environmental protection, land use, urban design, and related disciplines as full participants in an integrated design effort. It is further recommended that Dr. Christian Menn and Dr. Herbert Einstein, expert contributors to the Committee, be retained to consult on the design and construction of the Charles River crossing.

5. Continuation of this Committee.

We recommend that the Secretary ask this Committee to stay in existence during the design phase of the project to play an independent advisory oversight function. We recommend that the full Committee be convened on an as-needed basis at regular intervals, and that the following members of this Committee constitute an executive committee available to meet more frequently:

Stanley Miller, chairman

Joseph Beggan, City of Boston

Elizabeth Epstein, City of Cambridge

Joel Bard, chairman of the Land Use/Open Space subcommittee

Philip Caruso, chairman of the Traffic and Transportation subcommittee

Charles Redmon, architect, chairman of the Visual subcommittee

William Coughlin, Artery Business Committee

K. Dun Gifford, Citizens for Regional Transportation

Frederick Gleason, architect, Boston Preservation Alliance

Dan King, Citizens for a Liveable Charlestown

Robert O'Brien, Downtown North Association

Mark Primack, Move Massachusetts 2000

Robert Zimmerman, Charles River Watershed Association

6. Additional Studies.

The Committee recommends that the following studies be established by the Secretary:

· North/South Rail Link in Congress Street Corridor.

· Charles River Area Arterials

· Transportation/Land Uses North of the Charles River Air Quality Improvements

· Transportation Management and HOV Planning

Each of these studies should be performed with an open and participatory process, a multidisciplinary and multimodal transportation planning approach, adequate funding and firm deadlines established for findings and recommendations. A draft scope for each of these studies is included in this report; that scope should be reviewed and refined by the executive committee and by the advisory committee to be established for each of the studies. Affected agency, community, and user group representatives and Bridge Design Review Committee members, as appropriate, should be fully involved in the planning process.

North/South Rail Link

The Bridge Design Review Committee recommends that the Secretary begin a detailed feasibility study to examine connecting north and south rail networks by a tunnel in the Congress Street corridor to serve both commuter and intercity rail passengers. This recommendation reflects the conclusion of independent experts that there would be no advantage to a rail connection in the Central Artery corridor. This study should be a part of the MBTA's ongoing study of ways to improve and interconnect the intercity rail system in the Boston area. The study should investigate the proposed routing for such service; recommended construction methods and staging; estimates of construction costs and time frames; recommended implementation and staging schedules; funding sources and policy initiatives.

Charles River Area Arterials

The Bridge Design Review Committee recommends that the Secretary begin a detailed study of the interface between Storrow Drive, Memorial Drive, the Massachusetts Turnpike, and other related area arterials. The study should recommend proposed changes to improve the pattern of traffic utilization between regional and arterial roadways as well as the quality and accessibility of Charles River recreational facilities, and to reduce conflicts between traffic and recreation. It should consider design, construction, and operational measures necessary for timely implementation; funding sources and policy initiatives; recommended implementation and staging schedules; and the transportation, environmental, and public costs and benefits that will result therefrom.

Transportation/Land Uses North of the Charles River

The Bridge Design Review Committee recommends that the Secretary undertake a study to identify and evaluate transportation, access and service issues, and related land uses in the area north of the Charles River between New Rutherford Avenue, McGrath/O'Brien Highway, and Washington street. The Committee notes the jurisdiction of the cities of Boston, Cambridge, and Somerville over the redevelopment of this area and requests that the study be closely coordinated with said communities. At a minimum, the study should consider traffic and transportation issues, impact on existing roadways, access improvements, and public transportation opportunities. This study should assess opportunities for a variety of land uses in an integrated plan including partial or complete relocation of existing rail facilities. The study should investigate financing schemes to make possible suggested land use and transportation improvements.

Air Quality Improvements

The Bridge Design Review Committee recommends further study of ways to improve the air handling technologies of the tunnel sections of the CA/T Project, including but not limited to any tunnels selected in the Area North of Causeway Street as well as the quality of air being provided throughout the project. The study should include examination of alternatives for handling air that will provide the highest level of air quality possible for the approved plan.

Transportation Management and HOV Planning

The Artery/Tunnel Project provides both an opportunity and a necessity to improve the management of traffic in the Boston region and to encourage the use of forms of transportation other than the single-passenger automobile. A regional action plan is needed to encourage and accommodate the use of public transportation and high occupancy-vehicles (HOVs). Management plans should include effective incident management, communication of changing traffic patterns, and truck mobility (including those carrying hazardous materials). Mechanisms to examine include congestion pricing, automatic toll collection devices, managed lanes for priority traffic, pricing and availability of parking, and other such technologies and policies.

Issues to Be Resolved

Continuing effort will be made during the multidisciplinary design process to address several issues identified by the Committee. A workable off-ramp from the northbound Artery to Nashua Street will be vigorously pursued, as will accommodations for high-occupancy vehicles in a manner consistent with the regional HOV plan recommended by the Committee. Design and construction staging will attempt to minimize both construction and long term impacts to the Esplanade along the Charles Street Extension, Paul Revere Landing Park, the Registry Building, and other resources protected by Section 4(f). Charles and Millers Rivers open space, ramp infields, pedestrian, and bicycle facilities will be designed in conjunction with the Charles River bridge, other highway elements, and ventilation facilities to achieve Committee objectives and prior CA/T commitments, including an attractive and environmentally appropriate bridge design. There will be parallel design efforts and discussions with property owners aimed at reducing the impacts of viaducts, tunnels, and vents on the MGH development parcel near North Station and of ramps on the North Point Development in Cambridge. Environmental studies, including a possible Supplemental EIS/R, will address all impacts, including those involving the Charles and Millers Rivers, 4(f) resources, materials disposal, land use, and community areas. These impacts will be minimized to the extent possible.

Summary of Recommended Improvements to the Charles River Crossing

In carrying out its mandate to seek ways to improve the Charles River crossing of the Artery/Tunnel Project (the Proposed Action), the Committee reached consensus on the following improvements included in its recommendation. Both the selected Committee Improvement Package 8 and the other options given final consideration Committee (CIPs 3 and 5) are each a significant improvement over Scheme Z, in terms of traffic, open space and land use, and the visual appearance of the bridge and its associated ramps.

· Inclusion of a northbound on-ramp from New Sudbury Street in downtown Boston, serving the function of the former Traverse Street on-ramp that was deleted from the DSEIS version of Scheme Z. This directly benefits the North End and Charlestown by reducing traffic on Keany Square, North Washington Street bridge, City Square and New Rutherford Avenue. It also benefits the entire Boston downtown area -- political, residential and business interests had been unanimous in criticizing Scheme Z for eliminating the Traverse Street on-ramp.

· Direct connections (without having to cross the Charles River twice, as is the case in Scheme Z) via tunnels in the North Station area between Leverett Circle and the Central Artery southbound and Central Artery north-bound. All final options eliminate double river crossings, thereby reducing vehicle miles travelled and reducing the number of lanes crossing the river from 16 in Scheme Z (or 18 if Ramp WCN had not been deleted), to a maximum of 13. The recommended CIP 8 has 11 bridge lanes and two tunnel lanes. By reducing the volume of traffic on the bridge, the width of the bridge, and the number of ramps north of the river, elimination of the double river crossing benefits the interests of pedestrians, cyclists and others seeking more parkland along the riverbank; boats going under a significantly narrower bridge structure; those seeking to reduce pollution (by reducing vehicle miles travelled); and the developers and users of North Point.

· Reduction in the number, width, and height of bridges over the Charles River. The Committee has considered options that include no bridge (the all-tunnel option), combination bridge/river tunnel options, or solely bridge (either single-deck or double-deck). Instead of Scheme Ts three bridges (or four if the WCN ramp had been included in the project), all final options have a single bridge and reduce the height and the width of Scheme Z's crossing by about one-third. The single-deck bridge in the recommended CIP 8 is substantially narrower (196 versus 275 feet), and has lower towers (205 versus 335 feet). The bridge is far more visually appealing than Scheme Z's bridges. Though not symmetrical, CIP 8 has much less visual mass over the river, less impediment to navigation, and superior aesthetic appearance and opportunities for park uses along the riverfront. Having a single, and a lower and narrower, bridge benefits the developers and users of North Point by having less structure looming over the development area, and others who will see a much more aesthetically pleasing bridge from either near or far -- whether from Charlestown, East Cambridge, the North End, the Esplanade, or the North Station area.

· Reduction of impacts due to ramps in the North Point area in Cambridge, by placing the portions of them nearest the Charles River underground, thereby reducing their height and intrusion on planned developments in the North Point area and benefiting future park uses along the Charles River and in an improved Millers River area. Scheme Z's six loop ramps in North Point have been reduced to two in OP Sand the higher of the loop ramps is 65 feet lower than in Scheme Z. This benefits users of future parkland along the north bank of the Charles River, as well as the developers of the North Point area itself.

· Reduction in the height (by 25 feet) and width (by 95 fret) of viaducts near Charlestown, and fulfillment of previous commitments to provide pedestrian access to the Charles River via the Millers River area. This benefits the Charlestown community, which will have less visual and noise intrusion into their residential area and the newly created park around City Square, as well as pedestrians who want to walk to the riverbank.

· Improvement in the quality and quantity of open space along the Charles and Millers Rivers. The closest ramp to the Charles River is 120 feet away, as compared to 45 feet in Scheme Z, and structures over the mouth of the Millers River are reduced. These changes afford a significantly better opportunity to fulfill the Chapter 91 commitments of the CANA license and to implement the MDC's planning for the Charles River Reservation. The better highway design makes the CA/T mitigation commitments to improve this open space more cost effective, benefiting residents of Beacon Hill, Cambridge, Charlestown, and the entire region.

· Identification of a separate corridor (in the Congress Street area) for a future rail link between north and south (both intercity and commuter rail) that is compatible with the Artery/Tunnel Project as a whole. This benefits those who seek a viable corridor for intercity rail as well as those who want an improved commuter rail system with the capacity for trains to distribute passengers throughout the downtown, at North Station, Post Office Square, South Station, and Rack Bay.

In all options considered by the Committee (described on the preceding pages), the Committee has worked from the premise that the Artery/Tunnel Project could cross the Charles River in a manner that would enhance the region in general and the immediate area of the crossing in particular, as compared both with present conditions and with the proposed Scheme Z.

The Committee strongly believes that Scheme Z minimizes construction cost at the expense of important environmental and community values. Several project components developed since the SEIS/R reduce impact to those values and should be regarded as basic parts of any Charles River crossing alternative and included in the basis for cost comparisons. These include the land-based tunnel connections between Leverett Circle and the Artery south of Causeway Street, which eliminate double river crossings, reduce the width of structure over Paul Revere park, the Charles River and its banks. They are a prerequisite for improved bridge designs that reduce the number of bridge piers in the river and have less visual impact on nearby parkland. These tunnel connections also permit replacement of the Traverse Street on-ramp with a Sudbury Street ramp without additional structure in the park and river. The net incremental cost above Scheme Z of these connections is approximately $160 million, and this is a threshold that should be used in comparing final options considered by the Committee.

[Go to the top | Vertical file | CA/T documents | Home ]