1991 CA/T FSEIS

U.S. Department of Transportation, Central Artery (Interstate 93)/Third Harbor Tunnel (Interstate 90) Project, Boston, Massachusetts: Final Supplemental Environmental Impact Statement (Boston: Mass. Dept. of Public Works, January 1991), pp. 8-13.


Background: The following extract from the FSEIS explains the reasons the state chose Scheme Z as the final design for the Charles River crossing.


3 PROJECT CHANGES AND REFINEMENTS

Since 1985, the design of the Preferred Alternative has been developed to improve traffic operations, to mitigate potential impacts further, and to address issues identified for further design study in the approved 1985 FEIS/R. The Final SEIS describes the alternative designs considered after the approved 1985 FEIS/R in developing the Proposed Action. Part II of this Final SEIS contains a detailed analysis of the three major changes -- Area North of Causeway Street (crossings of the Charles River), South Boston Bypass Road, and toll plaza relocation -- along with a comprehensive evaluation of alternatives considered for materials disposal.

This Final SEIS describes design changes since the approved 1985 FEIS/R and further design refinements since the Draft SEIS/R. The effort since publication of the Draft SEIS/R has been to focus on those major issues that have been of concern throughout the lengthy project review process that began nearly 9 years ago. Two of those issues -- the Charles River crossing and materials disposal at Spectacle Island -- have generated the most public and agency review comments, and the plans for both have been substantially improved since the Draft SEIS/R.

3.1 Area North Of Causeway Street/Charles River Crossing

Since the Draft SEIS/R, design refinements have resulted in fewer impacts to the river and both its north and south banks. In response to the U.S. Coast Guard, USACE, and other agency and public comments, long-span bridges have been incorporated into the design (see Figure S.2), reducing the number of support piers in the river (see Figure S.3). (See also Sections 14.2.1 and 14.3.1 of the 1990 FSEIR.) The northbound Ramp W-CN has been eliminated, reducing the overall bulk and size of the river crossing. Ramp CS on the north bank has been relocated to eliminate encroachment of this ramp on the Charles River and to facilitate construction of the proposed riverside walkway/bikeway in a sunlit rather than shaded area.

3.1.1 Alternatives Considered

Overview. The Charles River crossing is one of the three major design changes since the approved 1985 FEIS/R. Part II of the 1990 FSEIR contains a complete analysis of design alternatives for this area, including full environmental analyses of the most promising options. This area also is one of the subjects of Part III of the 1990 FSEIR which includes the Final Section 4(f) Evaluation. A total of 32 design options for connections between the Central Artery and Leverett Circle/Storrow Drive were considered for overall viability. In 31 of the options, 1-93 is carried on new bridges across the Charles River and the Central Artery North Area Project (CANA) ramps provide connections between 1-93 and Route 1. An all-tunnel concept also was developed. It was determined to be not workable because of the following reasons: construction of mainline tunnels appears to entail a high risk of damage and prolonged disruption to the Orange Line tunnel; the weaving sections on 1-93 would be shorter than the current high-level bridge weaves which are being improved by CANA; there would be serious conflicts with commuter rail lines in Charlestown; and there would be major construction conflicts with Charles River navigation and North Station rail service, The all-tunnel scheme does not avoid parkland and has major construction impacts on parks; it would also add at least $1.2 billion to the project cost. A more detailed discussion of the assessment of the all-tunnel alternatives is contained in Section 6.2.8 of this Final SEIS.

After the Draft SEIS/R, attention focused on the comparison between two schemes, T Modified and Z Modified, as a result of public and review agency comments. Alternative T Modified (Charles River tunnel concept) uses tunnel connections behind North Station to connect Storrow Drive with the downtown Artery and makes the connections to the north in a tunnel under the Charles River. Alternative Z Modified (viaduct concept), the Proposed Action, makes both the northbound and southbound connections on viaduct on the north side of the river. These options were first examined in the Draft SEIS/R as to their constructibility, effects on traffic and transportation, and impacts on Charles River open space and other environmental resources. Both schemes relocate the main river crossing near the railroad crossing to North Station and remove the existing 1-93 bridge. This alignment of mainline bridges concentrates transportation facilities in a narrower corridor allowing the expansion of Paul Revere Landing Park, but it affects the Millers River as a result. Z Modified minimizes conflicts with pedestrian access to the MDC locks walkway at the new Charles River dam from Causeway Street, while T Modified has a highway exit ramp between the MBTA station and the park entrance. On the north bank of the Charles River, neither of the options would substantially impede pedestrian circulation on a permanent basis; the Z Modified alignment would cover a broader area than T Modified, but both schemes have essentially the same functional effect on public use of the Charles River and its open space corridor (see Figure S.4).

During the construction period, all of the options would result in temporary disruptions of pedestrian circulation at various locations for short periods of time; T Modified would result in a major negative construction period impact to the Charles River. Scheme Z Modified is the most constructible solution involving substantially less disruption to vehicular and commuter railroad traffic than other alternatives.

Z Modified provides the best overall solution to traffic operations and is the only scheme that provides adequate mainline weaves between the Sumner/Callahan Tunnels and Storrow Drive. As described in the Section 4(f) Evaluation, scheme Z Modified is functionally equivalent to scheme T Modified with regard to the 4(f) properties affected, while T Modified has major park access impacts at Causeway Street and substantially worse construction period impacts on parkland. Z Modified has lesser overall land use impacts and essentially the same long-term aquatic resource impacts to the Millers and Charles Rivers and to other impact categories. Z Modified has substantially fewer construction period impacts to transportation facilities and aquatic resources. Through a comprehensive mitigation program, the Proposed Action will result in a substantially improved Charles River corridor as well as a better transportation system.

3.12 Mitigation

A comprehensive mitigation plan for effects of the project in this area, particularly on parklands, has been developed to go along with the design modifications that have directly reduced those impacts. The Department and the MDC have agreed on these comprehensive measures. The MDC will take a lead role in the planning, design, construction, ownership, and management of the new parklands created. A Citizens Advisory Committee and Bridge Design Review Committee will participate actively in further detailed design.

Specific portions of the mitigation are compensation measures for impacts on previous CANA project commitments (see Figure 3.5). They are: the acquisition of private land on the north bank of the Charles River; a pedestrian connection under the North Washington Street bridge to Tudor Wharf; walkways across the MBTA railroad bridge; an improved path along the Charles River and redeveloped entrance to the Millers River; and improvement of the areas underneath the viaducts, with access from Rutherford Avenue.

Other portions of the mitigation commitment address Artery/Tunnel Project impacts on the extension of the park corridor, both in specific locations and as a whole. They include the improvements to bridge and ramp designs mentioned in Section 3.1, above. Noise barriers will be incorporated, subject to design review.

  • Paul Revere Landing Park, south bank, will be reconfigured and expanded south to Causeway Street and east to Lovejoy Wharf, where walkways and ferry terminals will be constructed. The new south bank pedestrian environment will extend upstream under the bridges as far as the MBTA walkways, and a structure under the bridges will house an active use such as a visitors center or food vending. A new Portal Plaza will be created on Causeway Street, and a pedestrian underpass will be provided at the North Washington Street bridge from Lovejoy Wharf to the North End Park.
  • Paul Revere Landing Park, north bank, will be reconfigured, restored, enhanced, and expanded westward to the new highway bridge and a pedestrian underpass to Tudor Wharf provided. The Department will pay for master planning of the Charles River Basin extension and will pay for the design and construction of new parks on the MDC-owned Nashua Street and GSA parcels and the newly acquired north bank waterfront. Many improvements will be made prior to highway construction. The MDC maintenance facility will be relocated from the GSA parcel.
  • Leverett Circle will be reconfigured, relandscaped, and enlarged. Pedestrian overpasses will be reconstructed with one or two new overpasses on the Nashua Street parcel. Historic buildings will be improved at the old dam, and site improvements including new walkways will be made on each side.
  • MBTA pedestrian walkways will be extended on each side of the railroad bridge, and a pedestrian bridge will be provided from O'Brien Highway, under the arches of the MBTA Green Line viaduct to the GSA parcel.
  • A 100-foot-wide strip of private river front land in the North Point area will be acquired and developed as parkland. As indicated by master planning, the MBTA bridge stub will be improved as a park or removed from the river. A 100-foot buffer zone will be created next to the loop ramps.
  • Improvements to the Charles River lagoons for skating and swimming will be studied, and Lee Pool will be improved and enlarged.
  • The Longfellow Bridge will be lighted and restored.

3.l.3 Progress Since The 1990 FSEIR

The visual and environmental impacts of Z Modified continued to be the most frequent concern expressed by both supporters and opponents of the project in response to the 1990 FSEIR. Comments ranged from adjustment of ramps or mitigation features to complete replacement with an all-tunnel alternative.

In terms of its scale and aesthetics, the interchange structure under Z Modified is over 400 feet from the nearest community, Charlestown, and over 1,500 feet from residential development at Lechmere Canal and more than 2,400 feet from the rest of the East Cambridge residential neighborhood. It will be visible from only a marginally greater surrounding area than the existing 1-93, and will be virtually hidden from view in East Cambridge. From Charlestown, the views from the edge of the community will be primarily of the elevated mainlines, much as they are at present, but of a larger structure.

The area of scheme Z Modified's elevated interchange is 49 acres, of which the loop rams account for 25 acres; in comparison, the CANA project interchange (no-build) covers 40 acres overall, its loop ramps 22 acres. In both CANA and scheme Z Modified, approximately 1 acre of viaduct would be located behind North Station, but this would not preclude development.

There is a strong commitment by the Department to high-quality design of the bridges, both as seen from a distance and by park users underneath them, and these bridges have the potential to create a positive gateway to Boston for drivers and to become objects of civic pride. Design of ramps and the surrounding buffer strip provide many opportunities for a higher-quality appearance than is typical for standard highway interchanges and for screening much of the inner ramp system and underlying structure from view, While the interchange is higher than current adjacent warehouse uses, plans for North Point in Cambridge and the North Station area m Boston include buildings more than twice the height of the ramp system.

The 1990 FSEIR contains an analysis of shadows of the bridge structures on the Charles River which concludes that they are of limited extent. Subsequent shadow studies using the same CADD model show that 3 PM December shadows (worst-case) would extend only to the median of New Rutherford Avenue and not to residences in Charlestown. The effect of shadows on navigation had been raised in connection with the earlier bridge design with more piers in the river. Consultation with the U.S. Coast Guard and MDC personnel concerned with navigation in the river concluded that shadows would not be a major problem with bridge piers located as committed in the 1990 FSEIR.

Mainline Tunnel Alternatives. The inadequacy of mainline tunnel schemes has become more evident with the submittal of additional tunnel schemes just prior to and during the 1990 FSEIR review process.

An all-tunnel crossing scheme (4.02) was submitted to the Department in sketch form by Mr. Stephen Kaiser of Cambridge, Massachusetts, shortly before publication of the Draft SEIS/R. Reasons why this scheme was not acceptable are explained in the 1990 FSEIR, Chapter IIB-1.3. Two additional schemes were recently submitted in sketch form (5.01 and 3.0) and are analyzed in Section 6.2.8 of this Final SEIS.

Mr. Kaiser prepared a list of 24 design, construction, and operational issues and problems attendant with his original all-tunnel scheme. The additional schemes attempt to improve the most serious operational issue, very inadequate weaving sections south of Causeway Street, and the constructibility problem, but none of the issues is adequately addressed in the revised schemes.

Mainline tunnel options 3.0, 4.02, and 5.01 pose many distinct construction problems which threaten service and structural integrity of the MBTA Orange Line tunnel and commuter rail facilities and require the underpinning of the piers supporting the 1-93 bridge over the Charles River, Analysis of the more recent schemes (5.01 and 3.0), which increase the separation between the highway tunnels and the Orange Line, strengthens the conclusion that an all-tunnel scheme would have major and potentially unsolvable construction problems of extraordinary magnitude for reasons detailed in Section 6.2.8 of this volume. Similarly, multiple tunnel connections under the North Station railroad platforms would disrupt commuter rail service for 2 years or more. Navigation would be largely disrupted for prolonged periods over many years by a large floating dredging platform, and tube fabrication would disrupt the proposed North Point development area, the GSA park site, and the Charles River Recreational Area upstream of the railroad bridge for the duration of Artery/Tunnel Project construction, which would be extended by 2 to 4 years. In addition, 1-93 bridge pier replacement and tunnel excavation could damage the lock mechanisms at the dam.

Even if these construction problems could be overcome, the tunnel scheme would not result in an acceptable highway design. Scheme 4.02 was improved during further study but still had very inadequate weaves on the mainlines south of Causeway Street, and would permanently conflict with commuter rail service north of the Gilmore Bridge. These problems are intrinsic to lowering the profile of the mainlines to provide adequate cover under the river. The complex geometry of the stacked tunnels in schemes 3.0 and 5.01 does not provide for required clearances. Even if a side ventilation concept is assumed, which would conflict with several ramp connections, these schemes still would result in mainline and ramp roadway grades too steep for acceptable traffic operations. Also, short weaves would remain.

The all-tunnel alternatives also have major Section 4(f) parkland and historic impacts, including the following: a permanent taking of part of the Nashua Street park parcel for an open boat ramp connection to Leverett Circle, disruption of the Charles River Extension Recreation Area and GSA park parcel during sunken tube construction, prolonged restriction of access to all of the Charles River from the Harbor, structural risk to the historic Registry Building, substantial effect on or possible foreclosure of the development of a new sports arena at North Station, relocation of Nashua Street, and tunnel construction very close to the Spaulding Rehabilitation Hospital and new Suffolk County jail, potentially damaging those buildings. There would also likely be probable adverse impacts from ventilation structures to the Causeway/North Washington Streets Historic District and Paul Revere Landing Park, as well as disruption of the park and walkway across the new dam during construction, Two to five ventilation buildings would be needed throughout the Area North of Causeway Street.

In addition, the suggested benefits of the mainline tunnel options in creating large areas of future parkland above the highway tunnel, depend in part on bringing very large quantities of soil to the area after construction and creating two large hills above the ramps, some of which would be so close to the existing ground surface that they would normally be designed as open boat or surface roadways. Given realistic assessment of cost and materials disposal logistics, the additional ventilation requirements and importation of cover material for these mounds may make it infeasible to convert these essentially surface roadways to tunnels.

Traverse Street Ramp. The 1990 FSEIR contains an analysis of traffic impacts of reducing the footprint of the Charles River crossing by eliminating the Traverse Street ramp (and its counterpart in scheme T Modified). It was concluded that the environmental benefits of removing the ramp outweigh the effects on traffic. Because further design study may make it possible to reincorporate the ramp without increasing Section 4(f) impacts, the Department will continue to evaluate this aspect of the crossing (the analysis contained in the 1990 FSEIR is sufficient to assess the environmental consequences of replacing the ramp).

The 1990 FSEIR contains an analysis of surface intersections with and without the Traverse Street ramp. It concluded that the effect of removing the ramp would result in some additional congestion at certain local intersections and warrant left turn restrictions at City Square and Keany Square. However, no intersection would experience service failure.

Since the 1990 FSEIR, further analysis of surface intersections without the W-CN ramp has lead to revisions in predicted PM peak hour intersection delays without the W-CN ramp and for the no-build case (Table 1.14 in Part IIB-I). At City Square, the earlier analysis of build conditions has been confirmed (125 seconds of delay with W-CN compared to 119 seconds without the ramp, assuming a peak hour prohibition of northbound left turns to the I-93 on-ramp; the no-build estimate has been revised downward to 92 seconds. At Keany Square, further analysis concludes that without W-CN, southbound as well as northbound and westbound left turns should be prohibited, resulting in a 48-second delay, or 55 percent less than with the ramp. The Keany Square no-build case had been incorrectly analyzed as resulting in gridlock; there would instead be 83 seconds of delay in the no-build case. The 1990 FSEIR comparison to the no-build should accordingly be revised: delays without the W-CN ramp would be higher than the no-build only at City Square, while Lowell Square would have the same delay as in the no-build. This does not change the overall conclusion stated above.

In addition, new analyses of traffic and air quality impacts were performed for the peak hour 2010 year condition at the intersection of Mystic Avenue and Assembly Square Drive and Lombardi Street. These analyses concluded that while there would be 275 more vehicles per hour on Mystic Avenue without ramp W-CN than with the ramp, no violation of the Ambient Air Quality Standard would occur. Further, the exclusion of the ramp should not have any significant air quality impact when compared to the future no-build scenario.

Current Status. Because the Department is committed to creating a Charles River crossing that is as aesthetically pleasing and environmentally sensitive as possible, potential modifications to scheme Z Modified will continue to be evaluated as the project progresses. The Bridge Design Review Committee includes members of the communities surrounding the Charles River crossing, representatives of interested agencies and associations, architects and engineers, and is responsible for identifying and evaluating potential modifications to scheme Z Modified which might further lessen the environmental and aesthetic impacts of the crossing.

[Go to the top | Home]

[ Scheme Z chronology | CA/T documents | Contributed articles | Plans and pictures | Vertical file ]